Baker Hughes Geothermal Power Generation Equipment For Fervo Energy

Baker Hughes To Design, Deliver Equipment For Five 60-Mwe Organic Rankine Cycle Units, Including The Engineering, Manufacturing, And Supply Of Turboexpanders And Brush Power Generation Generator

2 minute(s) Read

Baker Hughes announced an award from Fervo Energy Company, a geothermal energy company, to design and deliver equipment for five Organic Rankine Cycle (ORC) power plants at Fervo’s Cape Station power generation project near Milford, Utah. Once operational, the five Cape Phase II ORC plants will generate approximately 300 MW of power to the grid, equivalent power to approximately 180,000 homes.

Baker Hughes’ equipment is designed to operate with Fervo’s Enhanced Geothermal Systems (EGS), resulting in a fully integrated power plant that drives scalability in sustainable baseload power generation. The award is for Fervo-exclusive surface power generation equipment leveraging Baker Hughes’ geothermal solutions portfolio, which spans subsurface and production technology through to power generation solutions.

“Baker Hughes’ expertise and technology are ideal complements to the ongoing progress at Cape Station, which has been under construction and successfully meeting project milestones for almost two years,” said Tim Latimer, chief executive officer and co-founder of Fervo Energy. “Fervo designed Cape Station to be a flagship development that’s scalable, repeatable, and a proof point that geothermal is ready to become a major source of reliable, carbon-free power in the US.”

Baker Hughes’ engineering and equipment scope for the project includes design and delivery of equipment for five 60-MWe ORC units, including the engineering, manufacturing, and supply of turboexpanders and the BRUSH Power Generation generator. The order, to be booked under the Industrial & Energy Technology segment of Baker Hughes, follows previous awards from Fervo Energy for subsurface drilling and production technologies from the company’s oilfield services & equipment business.

“Geothermal power is one of several renewable energy sources expanding globally and proving to be a vital contributor to advancing sustainable energy development,” said Baker Hughes chair and chief executive officer, Lorenzo Simonelli. “By working with a leader like Fervo Energy and leveraging our comprehensive portfolio of technology solutions, we are supporting the scaling of lower-carbon power solutions that are integral to meet growing global energy demand.”

The Cape Station project includes Cape Station Phase I, which is poised to deliver 100 MW of baseload clean power to the grid beginning in 2026, as well as Cape Station Phase II, which will generate an additional 400 MW and come online by 2028. The full Cape Station development has received permitting approval for up to 2 GW of reliable and renewable energy.

 

Share This Article

Related Articles

Google, Georgia Power For 96 MW Of Nuclear Uprates

764
Read Article

TVA Lands First US Construction Permit For BWRX-300 Reactor

679
Read Article

Georgia Power’s OpenAI Deal Wins Approval

519
Read Article

Continue Reading